Substantial Completion and Payment Under
Construction Contract
Fields Excavating, Inc. v. Western Water Co.
(Dec. 30 2004), 2004-Ohio-7143
Substantial completion does not entitle a contractor to
final payment and its retainage if the terms of the
contract provide otherwise.
Contractor was not entitled to interest accrued from the
date of substantial completion where contract
expressly stated that payment could be withheld until
all claims against the project had been settled.
|