FEATURE ARTICLE
The Top 10 Clauses to Watch for in
Construction Subcontracts: What Every Sub Should
Know
Contracts serve to govern how a concrete contractor does
its job, and whether or not the job will be profitable.
Navigating contracts and agreeing to terms that meet
each party’s needs can be difficult, especially
considering that a construction contract can be up to100
pages long. The subcontract can also reference and
incorporate the terms and conditions of preceding
documents, such as the prime contract and/or bid
proposal which can be up to 500 pages in length.
Usually the terms of the prime contract cannot be
changed, but sometimes the subcontract can be
negotiated. Because of this, concrete contractors need
to review and be familiar with the contract’s terms to
protect themselves from conflicts that may arise down
the road. Here are 10 common terms every concrete
contractor should watch for when entering into a
contract:
1) Order of Precedence
Typically, when multiple contract documents are used,
they will contain an order of precedence. This order
determines how the documents’ provisions are interpreted
and states which terms govern when there is confusion or
contradiction between contract terms. More often than
not, the purchase order is the controlling document,
followed by the request for bid, and then the
contractor’s bid. It is important to be familiar with
the order of precedence because a term may be defined
one way in the contractor’s bid, but it may be overruled
by a different document.
2) Dispute Resolution
Many times, construction contracts require dispute
resolution to be handled through an arbitration
proceeding instead of a formal lawsuit. There are times
when this can be advantageous, such as in particularly
complex construction, but there are times when this is
detrimental. For instance, if a contractor institutes an
arbitration with the American Arbitration Association
for an unpaid contract balance above $1 million dollars,
the filing alone will cost $13,250. While this fee is
only 1 percent of the sum at issue, it is much larger
than a typical court filing fee of $100. Additionally,
parties pay all arbitration costs, including the hourly
rates of arbitrators, which, collectively, can exceed
$1,000 per hour. Examine whether or not arbitration
would be beneficial each time you enter into contract.
3) Jurisdiction
Contracts usually specify jurisdiction in the event that
a project goes poorly and the parties end up in
litigation. It is not unusual for a contract to specify
jurisdiction in a state that is most convenient for the
party that drafted the contract – typically, the project
owner. Consider jurisdiction when weighing the pros and
cons of a contract as this can increase the cost of
litigation.
4) Plant Inspection
For some projects, particularly government-regulated
jobs, the owner or general contractor may specify the
right to inspect or audit the batch plant. Few things
are worse than when the owner’s engineer inspects a
batch plant to find everything in disarray. This
reflects poorly on the concrete contractor, even if the
plant is operating perfectly. Make sure the batch plant
operator is aware of the potential for inspection and
agrees to properly maintain its records, including all
batch tickets and design mixes. By the same token, it is
the concrete contractor’s responsibility to make sure
the operator is actively managing these records.
5) Liability for Strength
Any concrete contractor knows that concrete strength can
be affected by a variety of factors, ranging from the
quality of ingredients in individual batches to
procedures followed during curing. If the concrete does
not come up to strength sufficiently, the contractor can
be liable for an equally broad variety of damages,
including consequential damages for delaying a project.
However, if the cause for strength issue is not the
fault of the concrete contractor but of another party,
such as the batch plant, the concrete contractor must be
able to obtain recovery from that party. Consider
incorporating the terms of the prime contract, including
arbitration, into any other agreement entered into for
the project.
6) Liability for Design Mix
Subcontracts should spell out specifically who is
responsible for – and, consequently, liable for – the
design mix. It is to the concrete contractor’s benefit
for the owner’s engineer to design the mix and specify
exactly what should be included, however, sometimes
contracts are vague and merely address strength
requirements. Be sure the subcontract specifies that the
final decision belongs to the owner or general
contractor. This way, if the design mix becomes an
issue, responsibility will not fall on the shoulders of
the concrete contractor.
7) Naming the Design Mix
Confusing design mixes is one of the easiest mistakes
made in the field. If the subcontract spells out the
nature of the mixes, be sure they are distinctively
named, so that a batch plant operator or driver is less
likely to accidentally provide the wrong mix. For
instance, if there are two types of concrete with 4,000
psi strength but different mixes, give each mix a
distinctly different name to reduce the likelihood of
confusion.
8) Record Maintenance
Most subcontracts will require the proper maintenance of
records regarding the concrete, batches, placement, etc.
Even if the subcontract does not include such
requirements, it is a good business practice to maintain
scrupulous records. For subcontracts that contain
specific record-keeping provisions, it is vitally
important to follow the requirements as closely as
possible. This means establishing protocols for the
field and accountability for those charged with
maintaining records. Failure to maintain records the
right way can be a major impediment to resolving any
sort of conflict that may arise between the concrete
contractors and others on the project.
9) Testing Costs
Each subcontract should clearly spell out who is
responsible for independent testing of the concrete, and
more importantly, assign financial responsibility. While
it is customary for subcontracts to outline that testing
the batches and placed concrete is required, some do not
define who is responsible for that testing. Make sure to
create a subcontract that defines these expectations.
10) Provisions for Delays
It is rare for a construction project to be completed on
time. Because of this, each contract must include
provisions regarding handling delays, apportionment of
associated costs and how the project should proceed in
light of delays. Be wary of contracts that place an
inordinate amount of responsibility on one party as this
can be a warning sign of future trouble.
Overall, contracts should clearly spell out the
expectations and promises of the parties who sign the
document. Each provision has importance and none should
be taken lightly. Entering into a bad contract is equal
to building a project with bad drawings, as it only begs
for more trouble later. It is better to take the time
before signing a contract to be sure that everyone is on
the same page to avoid disagreements later.
This article was originally published in
ForConstructionPros.com.
Christopher M. Ernst
is a Partner and a member of the Litigation and Real Estate &
Construction Practice Groups. He can be reached at
cernst@bdblaw.com
or 216.736.4216.