|
July 2007
Volume 10, Issue 2
|
 
Buckingham, Doolittle
& Burroughs’
Real Estate &
Construction Practice Group presents Build On This
In this edition of Build On This, we provide brief summaries of significant court cases
and legal developments affecting real estate
and construction, and two feature articles.
David Kern
and Andrew Bernat
(Akron) discuss the construction industry's use of
the
completed contract method in the first article.
In the second article,
Tod Morrow (Canton)
summarizes an important
new decision from the Occupation Safety and Health
Review Commission that will particularly benefit employers
in the construction industry. For current information on Real
Estate & Construction Law please visit our
web blog,
buildonthis.com. As always, we welcome
your opinions and feedback. Thank you. |
|
Case Summaries
REAL ESTATE CASES
Equitable subrogation does not apply to benefit party
that failed to discover mortgage interest.
IndyMac Bank, FSB v. Bridges (10th
Dist. 2006), 169 Ohio App. 3d 389. A property owner,
Key, granted a mortgage in favor of International
Mortgage on January 12, 2000. Key then granted a balloon
mortgage in favor of Goss on January 25, 2000, which was
re-recorded on February 17, 2000. In January 2001, Key
sold the property to her son, Bridges. Bridges granted a
mortgage in favor of IndyMac on February 7, 2001. At the
closing, the closing agent disbursed funds to
International Mortgage to pay off the first mortgage
loan, and the remaining amounts were distributed to
Key. Goss did not receive any proceeds from the sale,
apparently because IndyMac's title examiner failed to
discover his mortgage.
Bridges subsequently defaulted on the loan, and IndyMac
received the entire proceeds from the sheriff's sale.
After the trial court confirmed the sale, Goss sought to
set aside the order of distribution. IndyMac argued that
since Goss originally bargained for second mortgage
position, he remained in the same position and therefore
suffered no prejudice by application of the doctrine of
equitable subrogation. The trial court agreed. The
court of appeals reversed, and held that equitable
subrogation was not applicable in the circumstances
because the fact that Goss did not receive any
distribution from the sale was due to IndyMac’s title
examiner's error. IndyMac was in the best position to
discover Goss's mortgage interest at the time of the
sale, and it failed to do so. Therefore, the equities
were not in IndyMac's favor.
_____________________________
Intent to claim title not
required to establish adverse possession.
Evanich v. Bridge, 9th Dist.
No. 05 CA 008824, 2007 Ohio 1349. Bridge appealed the
trial court’s determination that his neighbor, Evanich,
adversely possessed his property because the trial court
did not require the Evanich to prove intent to claim
title. The appellate court rejected this argument and
held that the doctrine of adverse possession protects
one who has honestly entered and held possession in the
belief that the land was his own, as well as one who
knowingly appropriates the land of others for the
purpose of acquiring title.
_____________________________
The tenant sought a declaratory judgment that the lessor
could not terminate her tenancy if she complied with two
settlement agreements. The trial court granted the
tenant's summary judgment motion, and the lessor
appealed.
Regency
Plaza, LLC v. Morantz, 2007 Ohio 2594 (Ohio Ct.
App. 2007). Appellant lessor sought a declaratory
judgment in the Franklin County Court of Common Pleas
(Ohio) that appellee tenant's lease was not indefinitely
renewable by her and that the lessor could terminate it
on 30 days notice. The tenant sought a declaratory
judgment that the lessor could not terminate her tenancy
if she complied with two settlement agreements. The
trial court granted the tenant's summary judgment
motion, and the lessor appealed. The parties
entered into two settlements. The appellate court held
the first agreed not to terminate the tenancy unless one
of three events made the lease void. Neither the lease
or settlement gave the tenant all rights to terminate
the tenancy, so no perpetual lease was created, and this
did not make the lease terminable at the lessor's will.
A presumption that a lease at the will of one party was
at the will of both did not apply because the parties'
intent was clearly stated. A provision that the lease
was void on a change in ownership was not triggered on
the property's transfer to the lessors' partnership or
limited liability company, as (1) they agreed the
transfer to the partnership did not void the first
settlement, (2) a lessor said neither transfer was done
to avoid the settlements, and (3) the lessors controlled
all entities with title to the property. If the lease
was defectively executed, under R.C. § 5301.01, it
created an equitable leasehold, as it was treated as
enforceable despite any deficiencies. The second
settlement agreed the lease was in full force and
effect. The first settlement leased no interest in
realty, so it did not have to comply with § 5301.01.
The trial court's judgment was affirmed.
_____________________________
Appellant lessees sought review of the judgment of the
Lake County Common Pleas Court (Ohio), which awarded
judgment to appellee lessor for holdover rentals and
other expenses as compensatory damages along with
attorney fees as the result of the lessees' failure to
vacate the leased premises upon the conclusion of the
lease.
Brunswick Ltd. P'ship v. Feudo, 2007 Ohio 2163
(Ohio Ct. App. 2007). Appellant lessees sought
review of the judgment of the Lake County Common Pleas
Court (Ohio), which awarded judgment to appellee lessor
for holdover rentals and other expenses as compensatory
damages along with attorney fees as the result of the
lessees' failure to vacate the leased premises upon the
conclusion of the lease. The lessees entered into
a five-year lease with the lessor. Although attempts
were made to renew the lease at a stated rental of $
1,900 per month, the parties were unable to reach an
agreement. After the expiration of the lease, the
lessees remained in the rental premises for four months,
during which time they paid $ 2,206 per month to the
lessor. The lessor, then, filed suit against the
lessees. The trial court found that, pursuant to a
provision in the parties' lease, the lessor was owed
double rent for the four months of holding over. On
appeal, the lessees contended that the trial court erred
by ignoring binding precedent holding that a "hold over"
clause providing for double rent was unconscionable and
unenforceable. However, the court reviewed the precedent
cited by the lessees and concluded that the case did not
support the argument that holdover provisions containing
double-rent terms were illegal; instead, the decision
accepted the legality of such a provision as long as it
bore some relation to the landlord's actual damages. The
court concluded that a double-rent provision for a
holdover tenant in a commercial lease was not, without
more, an illegal penalty provision. The court
affirmed the judgment of the trial court.
_____________________________
The Stark County Court of Common Pleas (Ohio) granted
the bank's motion for summary judgment and entered a
decree in foreclosure and reformation. The parents
appealed.
JP
Morgan Chase Bank, NA v. Qualls, 170 Ohio App.
3d 128 (Ohio Ct. App. 2007). Plaintiff bank filed
a complaint against defendant property owners (a son and
his parents) seeking foreclosure, deed reformation, and
quiet title. It sought to have the deed reformed to
transfer the parents' entire interest in the property to
the son, who was the sole debtor. The Stark County Court
of Common Pleas (Ohio) granted the bank's motion for
summary judgment and entered a decree in foreclosure and
reformation. The parents appealed. The parents
argued that the trial court erred in granting summary
judgment to the bank, including reformation of the deed,
and erred in denying their motion for partial summary
judgment. The appellate court held that the trial court
erred in granting summary judgment. The trial court
found that the deed contained a scrivener's error and
that the parents had intended to convey the entire
property to the son, rather than a one-third undivided
interest. As the record stood, the deed transferred to
the son an undivided one-third interest only, and the
note and mortgage identified him as the sole borrower
based upon the pledge of that undivided one-third
interest. Although the bank might be entitled to
equitable relief and/or recovery from a third party
after resolving the factual issues, the current extent
of the record under a summary judgment standard was
insufficient to support the trial court's "finding" of
scrivener's error. Construing the evidence in favor of
the non-moving party required a reversal on the issue of
the clear language of the deed and mortgage. The
judgment of the trial court was reversed and the cause
was remanded.
CONSTRUCTION CASES
Removal of the scaffolding and
the installation of guardrail not “active participation”
under Cafferkey.
Rockett v. Newark Builders Supply, Inc.
(5th Dist. 2006), 169 Ohio App. 3d 379.
Arrow Home Services, LLC was constructing a
residential home, and hired Newark Builders Supply,
Inc., to perform drywall work. Newark hired independent
contractors, Rockett and Hastings to sand the drywall.
Rockett, fell to the basement floor and died. His father
filed a complaint claiming negligence and wrongful
death. He argued that Arrow and Newark owed his son a
duty because the removal of scaffolding and a guardrail
constituted "active participation." The trial court
disagreed and granted summary judgment in favor of Arrow
and Newark. The appellate court affirmed finding that
removal of the guardrail and installation of the
scaffolding by the subcontractor and the removal of the
scaffolding and the installation of the guardrail by the
general contractor, as well as the absence of defendants
on the job site on the day of the incident, did not
equate to "active participation." Specifically, there
was no evidence the general contractor directed any of
the activity of the independent contractors or that it
gave or denied permission for critical acts that led to
the injury.
_____________________________
No unjust enrichment where
property owner entitled to maintenance pursuant to lease
agreement.
Am. R.R. Constr. v. Columbiana County Port Auth.,
7th Dist. No. 06 CO 14, 2007, 2007 Ohio 1568.
The Columbiana County Port Authority owned a
railroad right of way. It leased the right to operate
the railway to a railway operator. The Port Authority
made improvements to the line and the operator agreed to
maintain the track. When a train derailed, the operator
entered into a verbal agreement with American Railroad
to repair the tracks. American Railroad was not paid for
work performed because of the operator's bankruptcy.
American Railroad then billed the Port Authority, which
refused to pay. American Railroad filed suit for unjust
enrichment and the trial court entered judgment in favor
of the Port Authority. The court of appeals upheld the
trial court's determination that the Port Authority was
not unjustly enriched by the work performed by American
Railroad. The Port Authority did not enter into the
contract with American Railroad, and it did not receive
a benefit to which it was not entitled, based on the
operator's lease obligations to maintain the track. The
court held it would not have been equitable to hold the
Port Authority liable for the operator's obligation.
_____________________________
Appellants, an oil and gas producer and its parent
company, sued appellees, a landowner, a contractor, and
an insurer, in the Franklin County Court of Common Pleas
(Ohio) for negligence.
Ohio
Energy Assets, Inc. v. Grange Ins., 2007 Ohio
2732 (Ohio Ct. App. 2007). Appellants, an oil and
gas producer and its parent company, sued appellees, a
landowner, a contractor, and an insurer, in the Franklin
County Court of Common Pleas (Ohio) for negligence. The
trial court granted summary judgment in favor of the
landowner, and appellants sought review. The
landowner hired the contractor to clear a creek on the
landowner's property without telling the contractor the
producer's pipeline ran under the creek. The contractor
ruptured the pipeline. The appellate court held the
producer's claim that injury was foreseeable ignored the
contractor's possible common law duty to independently
find the pipeline, if he was an excavator. The landowner
could assume the contractor would observe any such duty,
so a reasonable, prudent person would not anticipate the
landowner's silence would lead to injury to the
pipelines, as a reasonable, prudent person would expect
an excavator's performance of his duty would prevent
such injury. Absent a foreseeable injury, the landowner
owed the producer no duty. Conflict on whether the
contractor was an excavator created a genuine fact
issue, so it was error to grant summary judgment. The
producer was not an invitee to whom the landowner owed a
duty because only the contractor was invited onto the
property and exposed to a danger while there, but
because the landowner could owe a duty to the producer
based on the foreseeability of the injuries, summary
judgment was improper. The trial court's judgment
was reversed, and the matter was remanded to the trial
court.
LOT DEVELOPERS USING COMPLETED CONTRACT
METHOD SHOULD EXERCISE CAUTION
By:
David Kern and
Andrew W. Bernat
The IRS’s Large and Mid-Size
Business Division (“LMSB”) has issued a directive to its
agents warning that there is a growing trend in the
construction industry resulting in the improper use of
the completed contract method (“CCM”). Generally, a
long-term contract for the manufacture, building,
installation or construction of property must be
reported under the percentage-of-completion method (“PCM”).
However, home construction contracts, and other real
property construction contracts that satisfy a two-year
test and a $10,000,000 gross receipts test, are not
required to use the PCM and instead can use the CCM.
Under the CCM, notwithstanding the timing of payment
receipt, the taxpayer doesn’t report income until the
contract is completed.
The LMSB directive contains five examples that agents
are to look for. In one example, the taxpayer, a land
developer, enters into a sales/construction contract to
provide improved lots but is contractually obligated to
make future common improvements, such as a clubhouse,
pool, resurfaced roads, etc. In another, the taxpayer is
a subcontractor hired by the developer to construct
roadways, sidewalks, utilities and other common
improvements within a residential community. In both
circumstances, the taxpayers treat the contracts as home
construction contracts and elect to use the CCM, thereby
deferring the recognition of income until all of the
contracted improvements are completed.
A home construction contract is a construction contract
where at least 80% of the estimated total contract costs
is reasonably expected to be attributed to the building,
construction, reconstruction or rehabilitation of
dwelling units in buildings containing no more than four
dwelling units and improvements to the building’s
associated real property. The LMSB directive indicates
that a team is currently working to clarify the
definition of “home construction contract” with
particular application to the above-described examples.
David Kern
is a Shareholder and a member of the
Business Law, Health & Medicine and
Trusts & Estates Practice Groups. He can be reached at
dkern@bdblaw.com
or 330.258.6489. Andrew Bernat
is an Associate in the Business
Law
Practice
Group. He can be reached at
abernat@bdblaw.com or
330.258.6504.
OSHA's Multiemployer Worksite Policy Declared Invalid
By:
Tod T. Morrow

The Occupational Safety and Health Review Commission (OSHRC)
recently issued a decision that prevents the
Occupational Safety and Health Administration (OSHA)
from citing general contractors for the safety
violations of subcontractors at construction sites. In
a major victory for general contractors, two of the
three OSHRC Commissioners held that OSHA’s Multiemployer
Worksite Policy is invalid as applied to general
contractors that have neither created nor exposed
employees to a safety hazard.
In Secretary of Labor v. Summit Contractors, Inc.,
OSHRC Docket No. 03-1622 (April 27, 2007),
the general contractor, Summit Contractors, Inc.,
was cited for scaffolding violations committed by one of
its subcontractors. Although no Summit employees were
exposed to a fall hazard, the company was cited under
OSHA’s Multiemployer Worksite Policy because it was
deemed to be the “controlling employer” on the
worksite.
Under OSHA’s Multiemployer Worksite Policy, employers
can be cited in four situations:
-
If they
expose their employees to a hazard (“exposing
employer”);
-
If they
create a hazard (“creating employer”);
-
If they
have the ability or duty to correct a hazard
(“correcting employer”); or
-
If they
control the work site (“controlling employer”)
With respect to general contractors, the rationale
behind the policy is that by virtue of their contractual
authority and supervisory responsibility on the jobsite,
general contractors have the ability to require and
ensure subcontractor compliance with OSHA safety
standards.
Summit Contractors, Inc., appealed the citation, arguing
that the Multiemployer Policy was inconsistent with a
specific safety regulation (29 C.F.R. § 1910.12(a)),
which provides that “[e]ach employer shall protect the
employment and places of employment of each of his
employees engaged in construction work by complying
with the appropriate standards prescribed in this
paragraph.” (Emphasis added.) The OSHRC agreed with
Summit Contractors and invalidated OSHA’s application of
the Multiemployer Worksite Policy to general
contractors. In so doing, the Commission was persuaded
by OSHA’s inconsistent application of the policy as well
as the inherent unfairness of holding general
contractors responsible for violations committed by
other contractors.
The Summit Contractors case is one of major significance
for OSHA and the construction industry. The decision
essentially reverses more than 30 years of case law that
upheld the Multiemployer Worksite Policy. Consequently,
the Secretary of Labor is expected to appeal the
decision to the U.S. Court of Appeals.
Tod Morrow is a Shareholder in the
Employment & Workers' Compensation
Practice Group. He can be contacted at
tmorrow@bdblaw.com or
330.491.5229.
KUDOS__________________________________________
Joseph L. Ackerman, Jr.
(West Palm Beach)
is listed in the 2007 edition of Florida Super Lawyers®.
He
has been recognized as a Florida Super Lawyer in his areas of
practice, Complex Business and Construction
Litigation.
Mark F. Craig
(Cleveland)
has been recognized as a rising star in his area of
practice, Construction Litigation. He is listed in the
2007 edition of Ohio Super Lawyers Rising Stars®.
Christopher M. Ernst
(Cleveland) will
be writing a monthly column on legal issues for
Concrete Today, a national publication in the
concrete industry. Mr. Ernst also published an
article for Builders Exchange Magazine
entitled, "My Lawyer Can Beat Up Your Lawyer."
Donald B. Leach, Jr.
(Columbus) and
Henry I. Reder
(Cleveland) were named as Leading Construction Law Attorney’s in the
2007 edition of Chambers USA.
David J. Lindner
(Cleveland)
has been recognized as a rising star in his areas of
practice, Real Estate Transactions and Real Estate
Litigation. He is listed in the 2007 edition of Ohio
Super Lawyers Rising Stars®.
Michael D. Mopsick
(Boca Raton)
is listed in the 2007 edition of Florida Super Lawyers®.
He
has been recognized as a Florida Super Lawyer in his areas of
practice, Business Litigation, Probate & Trust
Litigation, Construction Litigation.
Robert E. Pershes
(Boca Raton)
is listed in the 2007 edition of Florida Super Lawyers®.
He
has been recognized as a Florida Super Lawyer in his areas of
practice, Intellectual Property, Intellectual
Property Litigation, Construction Litigation.
SPEAKING OUT __________________________________
Presentations recently given…
|
Date |
Title |
Presenting Attorney |
Sponsored By: |
|
April, 2007 |
Faith Is What Makes the Impossible, Possible: 12
Steps to Lead with Character |
Nicholas T. George |
Heart-to-Heart Communications |
|
June, 2007 |
Ohio Mechanics' Lien Law: The Hows and Whys of
the Paperwork (General Contractors, Owners,
Architects, and Lenders) |
Donald B. Leach, Jr.
|
The Builders Exchange of Central Ohio |
|
June, 2007 |
Implementing Strategies to Minimize the Risk of
Mechanics' Liens and 'Paying Twice' |
Donald B. Leach, Jr.
Mark
F. Craig |
OSBA CLE Institute |
|
June, 2007 |
Implementing Strategies to Minimize the Risk of
Mechanics' Liens and 'Paying Twice' |
John
P. Slagter
Mark
F. Craig
|
Summit & Portage County Home Builders
Association |
|
June, 2007 |
What to Do When Construction Projects Go Bad in
Ohio |
Mark F. Craig
Robert A. Hager
Frederick M. Lombardi
Martin J. Pangrace
John C. Ross
|
Lorman Education Services |
|
June, 2007 |
Critical Documentation for Proving Liability and
Damages |
Robert A. Hager
Martin J. Pangrace |
Associated Builders and Contractors, Inc. of
Northern Ohio |
|
June, 2007 |
Modern Mechanics' Lien |
Martin J. Pangrace |
OSBA seminar |
|
June, 2007 |
Litigation of Liens - Litigation and Enforcement
of Mechanics’ Lien Claims |
Robert A. Hager |
OSBA seminar |
Save the date for these upcoming presentations…
|
Date |
Title |
Presenting Attorney |
Sponsored By: |
|
July 26
Columbus, Ohio |
Resolving Problems and Disputes on Construction
Projects |
Michael V. Passella |
National Business Institute
Click
here
to register
|
August 1
Hilton Inn West, Akron, Ohio
|
Partnerships, LLCs and LLPs: Organization and
Operation in Ohio |
Andrew W. Bernat
Steve A. Dimengo
Christopher M. Ernst
Robert W. Malone |
Lorman Education Services Click
here
to register |
|
September 5
Ohio
|
I Paid the Architect! Don’t I Own the Drawings? |
Henry I. Reder
|
Akron Bar Association Real Property/
Environmental Law Committee |
·
If you are interested in
obtaining information on upcoming seminars or would be
interested in having speakers from Buckingham, Doolittle &
Burroughs, LLP make a presentation to your organization,
please contact: Lorna J. Henderson, Client Relations
Administrator at
lhenderson@bdblaw.com or 800.686.2825 ext.
86473.
|
|
|
www.bdblaw.com
1.800.686.2825 - Buckingham Akron SM
1.800.682.2825 - Buckingham Boca Raton
SM
1.888.811.2825 -
Buckingham Canton
SM
1.888.843.2825 -
Buckingham Cleveland
SM
1.888.686.2825 - Buckingham Columbus
SM
1.800.682.2825 - Buckingham West Palm Beach
SM
Real Estate & Construction Web Blog
http://buildonthis.com/
ENJOY READING THE BUILD ON THIS?
BDB also publishes
Advisor, a
general law newsletter,
Business Compass, a Business Law newsletter,
BDB
Health & Medicine Reporter, a
newsletter geared towards the healthcare industry,
Trusts & Estates Bulletin,
a newsletter geared towards all individuals,
Workfor$e,
an Employment & Workers' Compensation newsletter,
and several
Special Alert publications that cover changes in laws
that may affect our clients.
|
Akron
#
Boca Raton
#
Canton
#
Cleveland
#
Columbus
#
West Palm Beach |
|
Build On This
contains articles delivered as a free service from
the Law Firm of Buckingham, Doolittle &
Burroughs, LLP (BDB) to make clients and friends
aware of legislative changes and laws affecting their
businesses and personal lives. If you enjoy
reading
Build On This, please tell a friend or
colleague. The Build On This is sent
only to subscribers who have requested it. Anyone can
sign up for a free subscription or view prior
Build On This by visiting our web site at
http://www.bdblaw.com/newpublications.asp.
To change where you receive Build
On This, please e-mail us at
mlaster@bdblaw.com.
If you have received
this message in error and wish to be removed from future
Build On This mailings, reply to this
message and indicate “REMOVE” in the subject field.
The material appearing in future
Build On This newsletters is meant to provide
general information only and not as a substitute for
legal advice. With regard to specific law issues,
readers of this newsletter should seek specific advice
from legal counsel of their choice.
In some jurisdictions, this newsletter
may be considered advertising. The hiring of a lawyer is
an important decision that should not be based solely
upon written information about our qualifications and
experience. Before you decide, ask us to send you
free written information about our qualifications and
experience. Buckingham, Doolittle & Burroughs, LLP
has endeavored to comply with all known legal and
ethical requirements in compiling this newsletter.
Buckingham, Doolittle & Burroughs, LLP does not desire
to represent clients based on their review of any
portions of this newsletter that do not comply with
legal or ethical requirements.
This article may not be reprinted without
the express permission of Buckingham, Doolittle &
Burroughs, LLP © 2007.
Home |
The People |
Practice Groups |
About the Firm |
Careers |
Clients |
Community
How to Reach Us |
News & Information |
Seminars |
Diversion
A Full-Service Law Firm Serving Six Cities
Akron • Boca Raton • Canton • Cleveland • Columbus • West Palm Beach
Questions or comments? E-mail us at
bdb@bdblaw.com
© 1998-2007 Buckingham, Doolittle & Burroughs, LLP
Read our Disclaimer
and Privacy Policy.
|
|
|