|
REAL ESTATE CASES
The
doctrine of adverse possession is disfavored and its
elements stringent.
Crown Credit Co. Ltd. v.
Bushman (3rd Dist. 2007), 170 Ohio App.3d 807,
2007-Ohio-1230. In Bushman, Crown Credit Co.,
Ltd. brought an action against its neighbors for
declaratory judgment as to ownership of a disputed
border area, and Bushman filed a counterclaim to quiet
title based on adverse possession. The Auglaize County
Court of Common Pleas granted Bushman’s motion for
summary judgment, and Crown appealed. The Appellate
Court reversed and remanded the trial court decision.
The Appellate Court held that to
acquire title by adverse possession an adverse
possession claimant must demonstrate, by clear and
convincing evidence, exclusive possession and open,
notorious, continuous, and adverse use of the disputed
property for a period of 21 years. Here, Crown
conducted a survey in 2004, which was accompanied by an
intent to exercise dominion over the border area such
that it was sufficient to disrupt the 21-year period
required for Bushman to acquire the area by adverse
possession. Crown entered the land by conducting the
survey of the property, including the border area, in
preparation for purchasing the property in 2004, posted
flags demarcating the border area, and properly filed
the survey with the Engineer’s office, giving notice to
the world that it intended to possess and control the
entire property. This defeated Bushman’s “exclusive”
possession.
Although Bushman’s maintenance of
the disputed border area was “open” for purposes of
adverse possession, the actual, notorious and adverse
elements necessary to establish ownership require more
than merely conducting activities on the disputed
property where others can observe. To be notorious for
adverse possession purposes, a use must be known to some
who might reasonably be expected to communicate their
knowledge to the owner if he maintained a reasonable
degree of supervision over his premises; in other words,
the use of the property must be so patent that the true
owner of the property could not be deceived as to the
property’s use. The Appellate Court went on to conclude
that Bushman’s use of the disputed border was not
actual, notorious, or adverse.
CONSTRUCTION CASES
Failure to
follow contractual notice provisions precludes owner
from backcharging contractor for alleged
construction defects.
Certek, Inc. v. The Ohio
State University (Ct. of Cl. May 2, 2007),
2007-Ohio-2750. OSU entered into a contract with
Certek to manufacture and install a laboratory module.
OSU approved the plans, and Certek completed its work in
December 2004. OSU first raised problems with the lab
module in a letter dated April 29, 2005. The contractor
argued that the modifications identified by OSU in this
letter were not part of the original approved design but
were actually improvements. Certek further argued that
it had no chance to modify the work as the notice came
after others had already made modifications. OSU, eager
to open the lab, hired other contractors who were
already on site to complete the modifications and
attempted to backcharge Certek for its costs.
The Referee determined that OSU
failed to provide timely notice under the contract,
thereby denying Certek a reasonable time to cure any
defects. As in Dugan & Meyers, the court
strictly enforced the notice provision – only this time
against the owner.
_____________________________
Unreasonably late finish prevents builder from
collecting full contract amount.
Morton Buildings, Inc. v.
Correct Custom Drywall, Inc. (Franklin App. June
7, 2007), 2007-Ohio-2788. This case arose from
construction of a 36,000-square-foot garage with a
contract amount of $126,438. Although the owner wanted
it built within 90 days, the signed contract did not
contain a completion date but did state that July 1,
2002 would be the “approximate delivery date” for the
building materials. Also, a third proposal, dated the
same day as the contract, provided that construction
would begin in late July and end in late August.
The owner testified that he signed
the original contract because the contractor guaranteed
that it would complete the garage by September 1, 2002.
The contractor denied that he ever guaranteed a
particular completion date.
As expected, the contractor
encountered delays in completion, some of which were
caused by plan approval and inspections. In April 2003,
the owner learned that construction was not likely to
finish before April 15, 2003. The owner terminated the
contract, having paid only $50,571 – approximately 40%
of the original contract amount.
Morton sued for breach of contract
and unjust enrichment, and the owner filed a
counterclaim for breach of contract. Following a bench
trial, the court rendered a verdict against Morton on
its claims, and against CCD on its counterclaim. Morton
appealed.
The Court of Appeals held that
although the contract failed to specify a completion
date, the law implies that performance must take place
within a reasonable time. If performance took an
unreasonable time, then a material breach of contract
had occurred. Thus, if one party to a contract
unreasonably delays its performance, the other party is
excused from its contractual obligations.
Here, it was clear that the parties
had intended a three-month construction period, and the
actual construction stretched over a year. Although
some delays were caused by the city, the Court found the
contractor more responsible. As a result of Morton’s
unreasonable delay, the owner was excused from its
payment obligation.
Further, the Court rejected
Morton’s argument that the owner’s instruction to go
forward with construction following the initial
three-month period was a waiver of the owner’s right to
terminate the contract for unreasonable delay. Because
there was no definite date on which the job was to be
finished, the owner could continue to demand that the
contractor finish the job without waiving any right to
timely performance. Finally, the Court rejected
Morton’s unjust enrichment claim, holding that Morton
failed to prove that the owner lured it into building a
garage that it did not intend to pay for.
_____________________________
A
corporation’s imputed knowledge of a safety violation is
sufficient to charge it with a “serious” violation of
OSHA Safety Standards.
Kokosing Construction
Company, Inc. v. Occupational Safety and Hazard Review
Commission (May 25, 2007), 2007 U.S. App. LEXIS
12835. The case arose from an accident during the
construction of an underground sewer line in
Cincinnati. The project required deep excavations,
which in turn required the use of de-watering pumps. In
order to provide power for the de-watering pumps,
Kokosing used construction-grade electrical cords
connected to portable generators.
The workers on the site also used
wire chokers to move equipment on the site. A wire
choker is a device that uses a multi-strand wire to form
a loop on each end.
Just prior to the incident, a
Kokosing foreman discovered two electrical cords and two
water-discharge hoses lying on top of a choker. The
foreman asked another employee to assist him in pulling
the choker out from under the cords and hoses. When
they attempted to pull the choker out, a wire protruding
from the midsection of the choker pierced one of the
electrical cords. Two employees suffered electrical
shocks.
OSHA conducted an investigation and
issued a citation for a serious violation. The
administrative law judge who heard the case determined
that the citation was properly issued. After the
Occupational Safety and Hazard Review Commission upheld
the decision, Kokosing appealed to the Sixth Circuit.
Kokosing argued that it had no
knowledge of the violation and that the knowledge of its
foreman was, at best, constructive knowledge. According
to Kokosing, the Commission should not have imputed the
foreman’s knowledge of the violation to the company.
The court stepped through two different earlier cases to
reach an answer.
In Carlisle Equip. Co. v. United
States Sec’y of Labor, 24 F.3d 790 (6th
Cir. 1994), the court found that as long as the
government can prove that knowledge of a risk could have
been obtained “with the exercise of reasonable
diligence,” a supervisor is considered to have
constructive knowledge. In an earlier case, Donovan
v. Capital City Excavating, 712 F.3d 1008 (6th
Cir. 1983), the court found that the actual or
constructive knowledge of the employer’s foreman or
supervisor can be imputed to the employer.
Putting these two case together,
the Court found that if the foreman could have found a
hazard through reasonable diligence, that constructive
knowledge would be imputed to Kokosing. Determining
reasonable diligence requires the Court to look at
several factors, “including an employer’s obligation to
inspect the work area, to anticipate hazards to which
employees might be exposed, and to take measures to
prevent the occurrence.”
In this case, the foreman knew of
the possibility of a hazardous situation. He admitted
that he knew the choker was old but still did not check
it for abrasions before he moved it. He testified that
he had been taught to protect electrical cords from
sharp metal. The Court found that the Commission drew
the logical conclusion that the foreman knew an old
choker could have abrasions that could pierce the
electrical cord, thereby presenting a hazard.
The Court determined that the
foreman’s constructive knowledge could be imputed to
Kokosing. Such knowledge was sufficient to uphold a
serious violation and a fine of $1,875. This case
serves to remind employers that what a foreman may not
know but should can hurt both the employees and,
ultimately, the company.
|